Hyatt Hotel, SAN FRANCISCO, CA

Cabling Installation & Voice & Data Service

HyattSF.jpgProject: Hyatt Hotel

Location: San Francisco, CA

General Contractor: Gibson Technologies

Architect/Engineers: Gibson Technologies

Electrical Contract: $428,750

Project Duration: 6 months

Description: Contra Costa Electric, Inc. was hired to perform new cabling installation work in The Hyatt Hotel which towers above the San Francisco skyline. This telecommunications services project required a significant amount of coordination because of the need to work in an operating hotel during peak season.
 
CCE installed new category 6 data cable and category 3 voice cable to over 750 guest rooms, meeting rooms, conference rooms and administration offices. Work included (1) MDF and (36) IDF's, multimode and single mode fiber and copper cabling for backbone and riser.
 
We were praised for our ability to work around guests schedule, working in and during critical times and places as well as the courtesy of our technicians towards the guests and hotel staff.